Newcastle Airport Gold and Silver Car Park Upgrade

Client: Newcastle Airport

Cost: $0.5M

Capability: Utility Infrastructure

Location: Williamtown

Duration: 13 weeks

Overview:

Newcastle Airport is one of Australia's fastest growing airports with over 1 million passengers each year. This project required the expansion of the Silver car parking area by an additional 62 parking spaces, reconfiguring of the Gold car park and a number of improvements to layout and function of passenger roadways.

Scope of work:

• An additional 62 parking spaces to Silver car park
• Reconfigure entry and exit points to Gold car park, boom gates and associated work
• Bus and traffic control
• Pavements, drainage and traffic devices

Highlights and challenges:

• Planning around the continued operation of the airport and terminal was the main objective in the successful completion of this project. Careful consideration of traffic and pedestrian management was undertaken and incorporated into the schedule. This resulted in minor changes to working hours as required to facilitate the operations without interruption
• All project objectives were met, the job was delivered on time, to budget, with high quality and safety outcomes