Billy's Lookout Subdivision

13/05/2019

Client: McCloy Group

Cost: $33.3M

Capability: Residential Subdivisions

Location: Teralba

Duration: 2014-Current

Overview:

KCE commenced work in The Billy’s Lookout subdivision in 2014 and work is still ongoing.

To date, KCE have completed Stages 1, 2, 3, 4, 5, 6, 7, 8, 9, 11, 12, 13, 21 and 22 and have commenced work on Stages 14 and 23. Other works have also included construction of a playground and construction of a 900m long sound wall. 

Scope of work:

• To date 406 Lots have been completed and work is currently underway on a further 18 Lots
• 9032m2 of retaining walls
• Vertically split (up to 3m in height) main entry road
• Total Volume of Earthworks Completed to Date - 236 114m3
• 6 stormwater detention basins
• Water booster station
• 5983m of new roads and drainage
• utilities installation (including water, sewer, electrical, NBN and gas)
• Road Stormwater – 5.6km
• Sewer Pump Station

Highlights and challenges:

• Split level road with a retaining wall up to 3m high between carriageways
• 2 x 70m long 600mm diameter thrust bores going under state rail lines and Toronto Road
• Substantial Unsuitable Material requiring treatment and replacement
• Steep Sloping sites